Most IT teams don’t have too few projects. They have too many started at once, some approved in principle but never funded, others funded but competing for the same three people. Good portfolio management fixes that with a few simple disciplines.

Two decisions, not one

Approval answers: is this worth doing? It looks at the problem, the benefits, the risks and how it fits the strategy.

Funding answers: can we pay for it now? It looks at the budget, the quote and the timing.

When the two are merged, projects get “approved” in a meeting and start without money, then stall. Keep them separate: a project can be approved and waiting for funding, and nothing starts work until it’s both.

A simple project intake

Every idea enters the same way, ideally from a template, capturing:

  • The problem, objectives and success criteria.
  • Benefits and justification.
  • Sponsor, manager, department and cost centre.
  • Estimated effort, funding request and target dates.
  • Initial risks, dependencies and related systems.

Score and prioritize ideas consistently, so the portfolio conversation is about trade-offs, not who argued loudest.

Run each project with the basics

  • Tasks and schedule with owners, dependencies and baselines.
  • Resources with allocation percentages, so you can see over-commitment.
  • Finances: costs by period, against the approved budget.
  • RAID log: risks, assumptions, issues and dependencies, each with an owner.
  • Change requests for scope, budget or date changes, with a decision recorded.

Connect projects to the real world

A project that buys laptops, signs a contract or opens a new site creates operational records. Link the project to those purchases, assets, contracts, tickets and locations. Then the portfolio shows not just plans, but what was delivered and what it cost.

Portfolio views that matter

Leaders need four answers, monthly:

  1. Which projects are at risk on schedule or budget?
  2. Where are people over-allocated across projects?
  3. How much budget is committed vs. spent?
  4. What should we stop, pause or speed up?

Share with vendors carefully

Many IT projects depend on suppliers. Share specific tasks with a vendor rather than the whole project, so they see what they need to deliver and nothing more.