The riskiest way to replace several IT tools is to switch them all off on the same Monday. The safest is a phased rollout with clear gates, where each phase builds on clean data from the one before. Here’s the two-wave approach we recommend.
Why two waves
Employees feel the service desk on day one: how they ask for help and how fast they get it. Contracts, purchasing, budgets and projects matter just as much but touch fewer people, and they depend on good asset and supplier data. So:
- Wave 1: service desk, service catalog, SLAs, assets and knowledge.
- Wave 2: contracts and suppliers, vendor portal, procurement, IT budget, projects and locations.
Phase 0: discover and design (weeks 1–2)
- Kick off with the sponsor, project lead and subject experts from the service desk, asset and contract management, finance and the PMO.
- Review current tools, ticket categories, SLAs and spreadsheets, and list tools being retired with their renewal and notice dates.
- Run short design workshops per area.
- Produce one configuration workbook: teams, routing, SLA targets, catalog items, roles, approval chains and cost centres.
Gate 1: the sponsor signs the workbook. Scope is now fixed; anything new goes through change control.
Wave 1: configure, migrate, train (weeks 3–6)
- Configure teams, routing rules, SLA policies, business schedules and the service catalog.
- Migrate people, departments, locations, assets and software from templates; import open tickets and key knowledge articles.
- Set up inbound email, Google sign-in, Slack or Teams notifications and two-step sign-in for privileged roles.
- Run user acceptance testing with role-based scripts.
- Train agents and admins; send the employee launch email.
Gate 2: UAT passed, migration reconciled, cutover complete. The service desk is live.
Wave 2: the business layer (weeks 7–10)
- Load contracts, letting AI extract key dates and values, then review them.
- Set up supplier records, reviews and vendor portal invites.
- Configure purchase approvals with separation of duties, budget lines and next year’s planning cycle.
- Set up project templates, programs and portfolio views; add locations and work-order routing.
- Test and train finance approvers, contract managers and project managers.
Gate 3: wave 2 UAT passed and training delivered. The full platform is live.
Hypercare (30–45 days)
Daily check-ins at first, then weekly. Tune routing and SLAs from real data, fix small issues fast, and hand over to customer success with a 90-day adoption plan.
Five things that make it work
- A named sponsor who signs each gate within days.
- Data in templates by week 3. Late data is the most common cause of delay.
- Decisions within three business days.
- Parallel running for a week or two before switching off the old service desk.
- Cutover timed to notice periods, so you aren’t paying for two tools for long.
Timelines by size
Smaller organizations can compress the plan; larger ones need more room. As a guide: about 8 weeks for 500 employees, 10 weeks for 1,000 and 12 weeks for 1,500.
IT Unison implements this plan for a fixed fee: Launch ($29,500, 8 weeks), Accelerate ($44,500, 10 weeks) and Transform ($59,500, 12 weeks), each including design, data migration, AI contract extraction, training and hypercare. A $9,000 Service Desk Quick Start is available for teams that want to begin with wave 1 only.